Appendix: System integration checklist
This section lists the tasks necessary to complete the system integration. Each task is a link to the corresponding instructions.
Installation:
| 1. | Install the power source mains plug |
| 2. | Install the equipment on the stand (optional) |
| 3. | Install the cooling unit (optional) |
| 4. | Install RCM on the power source (optional) |
| 5. | Mount the wire feeder on the robot arm |
| 6. | Connect the protective earth cable (optional) |
| 7. | Install the fieldbus module (optional) |
| 8. | Install the add-on cards (optional) |
| 9. | Connect the cables to the wire feeder |
| 10. | Connect the cables to the power source and RCM |
| 11. | Turn on the welding system |
| 12. | Install the wire guide tubes |
| 13. | Install the feed rolls |
| 14. | Install the gas supply |
Configuration:
| 1. | Connect to the AX Manager user interface |
| 2. | Configure network settings |
| 3. | Configure device settings |
| 4. | Configure robot settings |
| 5. | Configure fieldbus settings (optional) |
| 6. | Apply welding programs (configure memory channels) |
| 7. | Make a system backup file (optional). |